Phase II Expansion - Master Plan and Implementation
St. Mary's Hospital
Madison, Wisconsin
Madison, Wisconsin
This project is the largest and most dramatic expansion in the hospital’s 92-year history. Maintaining green space for the neighborhood residents was in the highest of interest.
Inpatient and Diagnostic, 202,000 SF
Ambulatory care - 40 prep. and recovery rooms
CVICU and CVOR - 4 OR’s and 15 patient rooms
CVIMCU - 30 patient rooms
Cardiac services with gymnasium
Central Processing
Inpatient surgery - 18 OR’s
Central Plant Expansion
Four new 2-megawatt generators
6,500 tons replacement cooling tower capacity
One new 40,000 MBH boiler to bring the total plant boiler capacity to 128,000 MBH
Structured Parking 715 car capacity
Renovation
PACU
Emergency department
Cardiac services
Henneman Engineering provided all mechanical, electrical, plumbing, fire protection, medical gas, lighting, and information technology design engineering services for this Phase II Expansion.
Completion Date
2007
Total Construction Budget
$117,000,000