Renovation of Hilton Coliseum and New Practice Facility

Iowa State University

Ames, Iowa

The Hilton Coliseum Renovation and Additions project will address code compliance and related facility improvements in the existing arena and include fire alarm system upgrades, expansion of the existing concourse, elevator repair/replacements, exterior elevated walkway repairs and seating upgrades to include both suite and club section options.  The new basketball/volleyball practice facility addition will provide full size practice courts for both the men’s and women’s varsity basketball programs, the women’s varsity volleyball program and related support spaces. 

The project is expected to be constructed in multiple phases and will require coordination with ongoing events at the facility.  Henneman Engineering is providing HVAC, plumbing, and fire protection design for this project.

Completion Date
2010

Total Construction Budget
$60,000,000